FEATURE NEWS

Get the Home You Want

Is Your Site Buildable?

About Construction Loans

Budget Estimating

Shopping For Home Design

Contractor/Supplier Tips

Be An Active Learner

Our Newsletter

OBS News Archive

Get More Info

 

HOME BUILDING GUIDE

Your Planning Guide

Guide Contents

10 Ways to Collaborate

Decision Making Process

Design/Build Matrix

Building Green

Contract Documents

Drawings

Specifications

Permits

Budget Estimate

Cost Analysis

Purchasing

Trade Contractors

Suppliers

Scheduling

Safety

Quality Control

Punch List

OWNER BUILDER COACH | SEMINARS | DOWN HOME RADIO | HOME BUILDING GUIDE

budget estimate heading

With a will to spend there is a way. - A. Wildavsky

A Budget is a financial plan for your entire Design/Build process. It is the dollar equivalent for all the work it takes to design and build your new home. You are NOT expected to create this document accurately at the outset of your experience so it's best to begin with estimates and refine your financial plan as time goes by.

The primary purpose of preparing a Budget is to understand and control costs. Beginning with estimates, one is able to guess the total dollar amount for the style and size of home on a particular lot. At the very least an Owner should be able to consider if the project is feasible once estimates are made. The total dollar amount can be broken into two categories: hard costs and soft costs. Hard costs include labor and material to build the house. Soft costs include everything else. The Budget format provided here outlines products and services which one utilizes during the Design/Build process.

The Budget estimate for hard and soft costs is a departure point for considering the scope of Drawings and Specifications. These budgetary considerations BEGIN early in the schematic phase of the Design/Build process. Consider the initial study of costs as an exercise in project feasibility. Based on your projection of costs, the Owner should be able to weigh and consider the Design/Build options.

With estimates prepared, attention can be given to the Budget review process:

  1. Identify priorities;
  2. Recognize trade-offs;
  3. Do cost/benefit analysis;
  4. Revise cost estimate.

The following percentage estimate of hard costs is a ball park guess. It simply is a beginning point for determining if the amount you have to spend is even close to the house you want to build. One should realize that this is a very VOLATILE estimate. For instance, if you choose the "Sub-Zero" brand refrigerator for your appliance package (and if comparable products are used), then you might as well accept that once you complete your estimate, you will hold the price tag on a very high-end, luxury house. If you purchase the "Sears Best Buy" brand refrigerator for your appliance package (and remain with comparable products), then your estimate will result in a medium-priced, custom house. There is a cost range from economy, to modest, to custom, to luxury which CORRELATES with the products and materials you choose to install in your home. Match material/product choices with the price category in which you can afford to build.

CONSTRUCTION BUDGET ESTIMATE BY PERCENTAGE OF HARD COSTS

(Includes Labor and Material ONLY)

PHASESNOTES
Excavation3 %Full Basement
Structural Concrete7 %Footer, Walls, Flatwork
Framing23 %Floors, Walls, Sheath, Trusses
Roofing3 %3-tab asphalt shingles
Windows4 %Vinyl to energy code
Plumbing5 %Rough and Finish
Electrical5 %Rough and Finish
HVAC5 %Rough and Finish
Masonry1 %Decorative only
Siding4 %Walls and Exterior Trim
Insulation2 %Floors, Walls, Ceiling
Drywall5 %Hang, Tape, Finish, Texture
Sewer Hook-up1 %Ditch and Connectors
Water Hook-up1 %Ditch and Connectors
Paint/Stain2 %Interior and Exterior
Trim Package12 %Cabs, Counter, Doors, Millwork
Garage Doors1 %2 Doors with Openers
Floor Coverings7 %Vinyl and Carpet
Appliances4 %Standard Brand in White
Deck1 %Structural and Finish
Storm water1 %Gutters, Downspouts, Drains
Exterior Concrete2 %Garage Apron and Sidewalk
Final Grade1 %Machine and Hand Work
100 %

The soft costs are even more difficult to estimate because they are in proportion to the hard costs. In other words, the higher cost of building creates higher costs in order to build. A review of the following items will provide a general guide of what one must take into consideration for soft costs. Assign a cost to these items based on their percentage of total hard cost estimate.

With a projected hard cost estimate of $150,000.00, your soft costs would increase the project budget by an additional 50% (or $75,000.00). The total cost of your construction project including hard costs and soft costs would be $225,000.00.

CONSTRUCTION BUDGET ESTIMATE BY PERCENTAGE OF SOFT COSTS

1.All Permits (may differ)8 %(depending on your state)
2.Builder's Overhead and Profit10 %(may vary greatly)
3.Site Survey1 %
4.Off-site Utilities10%
5.Clean-up and Recycle/Refuse1 %
6.State Sales Tax (may differ)8 %(depending on your state)
7.Landscaping2 %
8.Architect/Designer's Fee10 %(may vary greatly)
50%

Remain aware of the volatility of soft costs as well as hard costs. Take for instance the 10% allotment (or $15,000.00) for Utility costs which would go toward Storm water Management, Septic or Sewer Systems, and Potable Water. A system to handle storm water can be more expensive than a septic system and in some cases may be cost prohibitive to build for conformance to your local ordinance. Whether you rely on a public sewer or a septic system, you will want to investigate costs and buildable size restrictions on site before you purchase a lot or begin with construction plans.

Issuance of a Building Permit will also require proof of water availability. There may be a municipal water system to your site, but if not you must consider the cost of a well and pump system to service your home. These factors must be taken into consideration to determine if the 10% budget allotment for utilities is sufficient to cover costs.

The following list is a further breakdown of Builder's Overhead and Profit. The breakdown assumes a 10% fee of total hard cost estimate. For example, let's again assume your estimate of total hard costs will be $150,000.00. With Builder's Overhead and Profit at 10% the amount would be $15,000.00.

BUILDER'S OVERHEAD AND PROFIT BREAKDOWN

1.Phone, Fax, Mail5%
2.Outdoor Toilet5%
3.Office Equipment, Supplies5%
4.Rental Equipment, Tools5%
5.Automobile Gas, Maintenance5%
6.Temporary Heat, Power5%
7.Builder's Bond/Liability Insurance5%
8.Miscellaneous Hardware5%
9.Job Shack5%
10.Overhead Labor10%
11.Bid/Negotiations5%
12.Superintendent20%
13.Profit20%
100%

Keep in mind that this Budget Estimate is just a beginning point: it's a means for you to better understand how money MAY BE proportioned into various categories. For instance, let's consider Builder's Profit. On a $150,000.00 project, is it reasonable to expect a Builder to only make $3,000.00 in Profit? If you take over the duties of the General Contractor as an Ownerbuilder, wouldn't you want to experience more sweat equity? Then, why would you ever begrudge a GC from making more Profit on the management of a project?

Obviously, if you're hiring a General Contractor to handle all aspects of the construction of your project, you'll need to allow him/her to profit so the job can be done on time, in budget, with quality, and using qualified trades. You'll want your GC to stay in business and making a profit is the only way to insure it!

The following list is a further breakdown of the Designer's Fee. The breakdown assumes a 10% fee of total hard cost estimate. For example, let's again assume your estimate of total hard costs will be $150,000.00. With Designer's Fee at 10% the total amount would be $15,000.00.

ARCHITECT/DESIGNER'S FEE BREAKDOWN

1.Schematic Design15%
2.Design Development20%
3.Contract Documents40%
4.Bid/Negotiations5%
5.Construction Observation20%
100%

Keep in mind that your home design may be acquired from a stock plan service rather than hiring an Architect to provide this service. If you purchase a stock plan for $1,000.00 rather than spend $15,000.00 on full architectural services, then you've radically changed how money will be proportioned in your anticipated budget. This type of flexibility is what your Budget Estimate is all about!

Budgetary activity can be accomplished at a very rudimentary level literally months before construction begins. Your project may not be feasible now but that doesn't mean one shouldn't prepare for the future. It's never too early to look at three key ideas: objective, strategy, and plan.

An OBJECTIVE is a defined target or position that can be quantified; it is developed from an analysis of the situation at present and projected future development. A STRATEGY is one of the several ways possible to reach an objective. A PLAN is the detailed outline of activities which will be undertaken to satisfy the strategy selected to reach the agreed objective.

An example: You enjoy the home in which you currently live but realize there will come a time when you build a similar residence in a different architectural style. That's the situation: you understand your lifestyle but want to alter your homestyle. More objectives than one are possible, but you decide on one OBJECTIVE: to stick with a similar floor plan but change the motif and decor.

Several strategies come to mind. You can let the situation continue and wait until you find a house for sale which meets your expectations. You can remodel your existing home. You can create a ball park estimate for the new house and complete a feasibility study of Design/Build costs. There are a number of strategies possible but you select one STRATEGY as being most practical for your wants and needs: to do a feasibility study.

Your PLAN is: 1-go to the public library and review plan books or trade magazines for helpful ideas, 2-find a similar house for sale through a local builder and get the "asking" price, 3-use the "Budget Estimate" format for hard and soft costs to breakdown costs into discrete categories, 4-visit local Suppliers and choose products for your new house, 5-compare the quote from your local Suppliers with the percentage estimate, 6-complete the budget review process.

budget estimate

Remember: The primary purpose of preparing a Budget is to understand and control costs. Ideas must take shape and become quantifiable. Project familiarization requires one to move from generalities to specifics. What begins as a vague notion or a few sketches on the back of a napkin, evolves into an itemized list of services, products, and materials chosen specifically for your home design. Or, you may decide to purchase a pre-built home based on your desire just to get into a new home as quickly as possible.

Getting started on a Budget can be very exasperating with no formal training in business. The example described in the previous paragraphs suggests a "seat of your pants" approach but when you get serious, the Owner must take the time to produce a written PLAN OF ACTION.

As the pressures of starting a construction project increase, you'll begin to ask yourself, "Why are we doing this? What do we want from our lifestyle? How should we create our homestyle?"

Begin with a written statement of your OBJECTIVE. This statement will describe the purpose of your endeavor by defining your values and concerns. Try to answer questions like "What do we want this project to achieve?" and "What type of impact will me make on the community in which we live?"

Don't expect to write your objective statement in a few minutes. Take your time. Savor the moment. Go to a favorite cafe or park bench making this a special occasion.

Once your Objective has been defined, you'll begin to ask yourself, "When do we do this? How do we accomplish this? What are our financial goals for the next 24 months?" Your next step is to prioritize your activities so alternative schemes can be considered and general ideas become more definitive. By developing a STRATEGY, the Owner accepts that there may be multiple ways to reach one's objective, and ample time should be given to considering the options.

As you consider options, be ready to attach costs to the various phases of construction. What you're considering is a list of services, products, and materials for your home. This is a financial projection of what will happen if you go "this way" or "that way." Enjoy the luxury of being able to change your mind.

Now the options have been considered, the Owner is able to direct attention to a specific PLAN. This doesn't have to be fancy. Simply state how you expect to reach what it is you hope to accomplish. Establish hard and soft costs basing estimates on what you can afford and what you want, and compare them with the percentage guidelines. Go to the marketplace to check your estimates with actual costs. If the actual costs go beyond the percentage guidelines, consider a different strategy for reaching your objective or maybe begin to challenge your preconceived notions of what's a reasonable expectation.

Writing a plan of action will only be worthwhile if you review it regularly and revise it when necessary. Don't expect to get it completely right the first time, and allowances should be made for flexibility.

Your Budget Estimate is a LIVING DOCUMENT!

Email comments to:
Owner Builder Services -- Tom Landis

Visit the Owner Builder Coach for more free information:
http://www.OwnerBuilderCoach.com

 


Special thanks to Olympic Web Design for hosting.




Tom Landis © copyright 2008-2022 OwnerBuilder.com - All Rights Reserved